OffererTJC Engineering, Inc.
Contract NumberW912QR-09-D-0019-0005
Original Completion Date06 / 06 / 2010
Original Value$725,775.00
Type of ContractFirm Fixed Price
RolePrime Contractor
Award Date09/28/2009
Final Completion Date06/06/2010
Final Value$745.374.00
LocationFort Campbell, KY

Project Description

Final Evaluation Rating: Above Average

Included the abandonment of the existing domestic water supply lines located underneath the building and replacing them with new overhead domestic water supply lines located in the attic of the school building. Also included in the project will be incidental electrical and architectural work that is a result of the main plumbing work, minor asbestos abatement and exterior improvements.

The project was on a very strict and aggressive schedule in order to reopen the school as scheduled. Not only was the schedule adhered to, the date the work was accepted was one full month ahead of schedule.