OffererTJC Engineering, Inc.
Contract NumberW912QR-06-D-0008-0023
Original Completion Date10/02/2007
Original Value$1,429,134.00
Type of ContractFirm Fixed Price
RolePrime Contractor
Award Date12/21/2006
Final Completion Date10/02/2007
Final Value$1,431,015.00
LocationFort Campbell, KY

Project Description

Final Evaluation Rating: Above Average

TJC abated asbestos and demolished multiple bunkers including grinding debris 6 months ahead of schedule.  This project required extreme safety and environmental precautions.

Scotty Craig the superintendent accelerated work without jeopardizing human health or environmental safe guards.

This project exemplifies TJC’s ability to execute work aggressively without sacrificing essential project controls.