OffererTJC Engineering, Inc.
Contract NumberW912QR-06-D-0008
Original Completion Date12/20/2008
Original Value$183,418.90
Type of ContractIDIQ
RolePrime Contractor
Award Date06/18/2008 (Harsha) / 08/21/2008 (Caesar Creek Lake)
LocationHarsha Lake in Springfield, OH & Caesar Creek Lake in Waynesville, OH

Project Description

The metal surfaces inside the dam conduit was corroded and the sluice gates were leaking. TJC Engineering Subcontractors accessed the conduit, used balsting measures to abate lead paint and recoat the conduit and sluice gates. The floor of the conduit developed as a major obstacle in completing the project. TJC laborers constructed a dam inside the conduit and pumped water around to insure proper adhesion of metal products.

  • Harsha Lake (Task Order 0064) – $91,616.72
  • Caesar Creek (Task Order 0071) – $91,802.18