Offerer | TJC Engineering, Inc. |
---|---|
Contract Number | W912QR-06-D-0008 |
Original Completion Date | 12/20/2008 |
Original Value | $183,418.90 |
Type of Contract | IDIQ |
Role | Prime Contractor |
Award Date | 06/18/2008 (Harsha) / 08/21/2008 (Caesar Creek Lake) |
Location | Harsha Lake in Springfield, OH & Caesar Creek Lake in Waynesville, OH |
Project Description
The metal surfaces inside the dam conduit was corroded and the sluice gates were leaking. TJC Engineering Subcontractors accessed the conduit, used balsting measures to abate lead paint and recoat the conduit and sluice gates. The floor of the conduit developed as a major obstacle in completing the project. TJC laborers constructed a dam inside the conduit and pumped water around to insure proper adhesion of metal products.
- Harsha Lake (Task Order 0064) – $91,616.72
- Caesar Creek (Task Order 0071) – $91,802.18